Sheetpiling Recommences

Sheet piling works have recommenced, with the primary piling installations expected to be completed during February. All piling lines are being pre-drilled to facilitate installation, and vibration monitors continue to be in place, with vibration levels currently well within the prescribed limit of 5 mm/sec.

Following completion of the piling, bulk earthworks will progress to various levels to enable the installation of support anchors. Only minimal vibration is anticipated during the anchor installation works.